Energy Crops Case Study – Tredethick Farm Cottages, Cornwall

Crop for Energy

Tredethick Farm Cottages located in Lostwithiel, Cornwall is using miscanthus grass as a fuel to provide district heating to 8 holiday lets, a farmhouse and a swimming pool. Crops for Energy was commissioned by the farm owner/proprietor Tim Reed to assist in the initial feasibility study and subsequent management of the project. The first two days of technical support were provided at a discounted rate through the Resource Efficiency for Farms (R4F) Scheme managed by Rural Focus.

Background
Previously, the farm enterprise used 32,000 litres of oil costing around £19,000 per year. The main drivers for installing the biomass system included the rebates offered by the Renewable Heat Incentive (RHI) and the cost savings of woodfuel compared to heating oil. In addition, a centralised boiler would enable the ugly oil tanks to be removed which would improve aesthetics and free up space around each building. By growing their own fuel the farm will be self sufficient and also insulated from future fuel price rises.

Tredethick case study 3

Aerial view of Tredethick Farm Cottages showing boiler house
and plan of the heat distribution network.

Boiler choice
The initial feasibility study was carried out in August 2011. It was decided that the site was viable and that an existing barn would provide a suitable location for the boiler and fuel store. There are only a limited number of small scale heating systems available on the market that can use miscanthus chip. This is because miscanthus has the following combustion characteristics:

Four companies were approached for turn key installation quotes. The chosen system was a 199 kW Eta Hack wood chip boiler installed by Fair Energy Ltd who are based in Exeter. Eta boilers can deal with the challenging nature of miscanthus fuel.

Miscanthus chip is much less dense than normal wood chips and therefore this requires more storage space. Most of the miscanthus chip produced by the farm will be accommodated in the existing barn. Another disadvantage of using miscanthus as fuel is that its low density means that it is not possible to physically get enough fuel into the combustion chamber for the boiler to achieve its full capacity. As a result the ratings of boilers are downgraded so a 199 kW boiler has an output of 140 kW when using miscanthus.

The boiler, fuel store and heat distribution system was installed in 5 weeks from late December 2011. The most disruptive elements of the installation such as digging the trenches to lay the heat main were carried out in January which is the one point of the year when the holiday lets are unoccupied.

Fuel Supply and Storage
The district heating scheme requires around 340,000 kilowatt hours (kWh) of heating per year. From 2015 onwards this will be provided from just 5.7 hectares of miscanthus that was planted on the farm in May 2012. An establishment grant providing 50% towards the cost of planting was awarded by the Energy Crops Scheme (ECS) managed by Natural England. Until the crop reaches maturity, miscanthus chip will be purchased from an existing local grower.

Tredethick case study 1

Left: Miscanthus being planted at Tredethick Farm in May 2012.
The barn and holiday lets can be seen in the background.
Right: A mature miscanthus crop

The field growing the miscanthus is adjacent to the barn containing the boiler. As a result, when it is harvested the miscanthus chip need only be moved 420 metres from the furthest point. Once the crop is established the only cost to the farm will be its harvesting and some annual fertiliser inputs.

A 40 m3 fuel hopper (5m x 2m x 2m) needs to be filled 25 times a year with a front end loader. In summer this needs filling every 3-4 weeks whilst in the winter it might require filling every week. The ash pan is emptied every week and used as fertiliser on the field where the miscanthus is planted.

Capital and Operational Cost
The overall capital costs of the boiler installation, energy crop planting and project management was £171,040.

It is possible to establish, manage, harvest and store miscanthus chip for around £45/tonne if the costs are spread out over 16 years. This includes the ECS grant and allows for lost revenue from a conventional food crop. By replacing heating oil with miscanthus chip it might be possible to save over £14,000 per annum based on current prices.

The Government’s Renewable Heat Incentive (RHI) will provide an annual rebate to producers of renewable heat. The application for RHI accreditation was made to Ofgem in February 2012 and approval was granted in May 2012. The Tredethick boiler project is one of the first in the UK to be approved using an energy crop as a fuel. The table below indicates the potential returns from the scheme. Payments will be made on a quarterly basis.

Boiler rating

199kW

Total annual heat demand to be met from biomass boiler

320,000 kWh

Tier Break

199kW x 1,314hrs = 261,486kWh

Tier 1 tariff revenue

261,486 kWh x 7.9p = £20,657

Tier 2 tariff revenue

(320,000 – 261,486) x 2.0p = £1,170

Total annual RHI revenue (Tier 1 + Tier 2)

£21,827

 

The total savings and revenue produced by the scheme are £35,827 giving a simple pay back of 4.8 years. Over the 20 year tariff period the system could generate a net profit of around £544,000 based on current fuel prices.

Tredethick case study 2

Tim Reed of Tredethick Farm Cottages and Kevin Lindegaard of Crops for Energy with the Tredethick Boiler 

How Crops for Energy helped
During the project we have assisted Tredethick Farm Cottages in the following ways:

For Tredethick Farm Cottages it has been a smooth ride with very little hassle. Crucially they have not had to try and learn everything about bioenergy – they’ve simply employed us as trusted advocates to help them make the right decisions.

 

Project timeline

Feasibility study conducted

31st August 2011 

Quotes received from installers

Mid September 2011

Energy Crops Scheme application submitted

12th September 2011

Energy Crops Scheme application approved

4th November 2011

Start of boiler installation

Mid December 2011

Completion of boiler installation

27th January 2012

RHI accreditation application submitted

21st February 2012

RHI accreditation granted

14th May 2012

Miscanthus planted

24th May 2012

 

 Summary information

Boiler type

199 kW wood chip boiler

Installer

Fair Energy

Capital cost

£157,000

Amount of miscanthus chip required

Approx 89 tonnes/year

Amount of miscanthus planted

5.7 hectares

 

Contacts and more information

Crops for Energy
Tel: 0844 249 2901
Website: www.crops4energy.co.uk
Tredethick Farm Cottages
Tel: 01208 873618
Website: www.tredethick.co.uk
Resource Efficiency for Farms (R4F) Scheme
Tel: 08456 047 047
Website: www.businessanswers.info/rural/Resource-Efficiency-for-Farmers
Energy Crops Scheme
Tel: 0300 060 1624
Website: www.naturalengland.org.uk/ourwork/farming/funding/ecs/default.aspx
Renewable Heat Incentive
Tel: 0845 200 2122
Website: www.ofgem.gov.uk/RHI

 

© Kevin Lindegaard, Crops for Energy 2012